|
|
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
31 |
|
|
| | All months |
|
|
| | |
| Work Breakdown Structure |
In the following page you will find the project's work breakdown structure. |
Work-package No |
Workpackage title |
Lead contractor No |
Start month |
End month |
Deliverable No |
WP1 |
Project administrative and technical management |
GRNET |
10/05 |
12/07 |
D1, D7a-d, D22 |
WP2 |
E-learning platform |
FUB |
11/05 |
09/07 |
D3, D5, D6, D10a-d, D13a-b |
WP3 |
Training content |
UOM |
12/05 |
06/06 |
D8, D9, D11, D12 |
WP4 |
Training the tutors and SMEs |
GRNET |
01/06 |
03/07 |
D4a-b, D14, D16, D17 |
WP5 |
Dissemination actions |
GRNET |
10/05 |
12/07 |
D2, D19a-h, D20, D21 |
WP6 |
ICT Training Strategies |
DANUBE |
01/06 |
07/07 |
D15a-d, D18a-d |
|
| |
|
You are using IPv4
|
|
| |